Interface Testing of Junction Box
In September 2012, the RSN Junction Box engineering team* at the UW Applied Physics Laboratory achieved an important milestone: they conducted interface testing after connecting a prototype of a low-power junction box to three standard oceanographic instruments planned for deployment on the RSN system.
The low-power junction boxes are one of three types of secondary nodes that serve as a bridge between the RSN instruments and the Primary Infrastructure. The primary nodes provide 10Gb/s interfaces and 8KV power from the shore station. The Secondary Nodes are comprised of low- and medium-power junction boxes and low-voltage nodes, and these nodes convert the 1 Gb/s bandwidth and 375dc voltage interfaces from the Primary Nodes to the native interfaces needed by the scientific instruments. Each instrument has its own unique interface that handles power and communications with the junction box. Each junction box provides up to eight instrument ports that can be configured for 12, 24 or 48V and 10/100BASE-T, RS232 or RS485 data links. Nodes can be daisy-chained, thereby creating extensive expansion capabilities.
The three instruments connected during the testing were: a Vertical Acoustic Doppler Current Profiler (VADCP), a Conductivity-Temperature-Depth (CTD) instrument, and a pressure sensor. The goal was early identification, before full production begins, of any communications or power interface issues between the junction box and the scientific instruments.
Mike Harrington, the APL senior engineer leading work on the RSN secondary nodes, explained that the three instruments in this test were all first articles–the first unit received from a vendor–and that each had already been accepted after passing tests in the saltwater tank in the Ben Hall Laboratory.
One of the important discoveries made during testing was that the VADCP had a larger-than-expected inrush current when it was turned on, higher than the electronics could accommodate. A solution was found to reduce the inrush current yet allow the VADCP to start up properly. The CTD and pressure sensor each performed as expected and ran continuously for over two weeks as part of the testing.
Next step is for the junction box to go through formal First Article testing. In spring 2013, it will be integrated on its deployment frame with all attached instruments and will go through final integration testing in preparation for deployment in summer 2013.
*RSN Junction Box Engineering Team Members
Mike Harrington – Senior Engineer
James Tilley – Electrical Engineer Board Design
Jesse Dosher – Electrical Engineering Control Systems
Geoff Cram – Mechanical Engineering Lead
Patrick Waite – Mechanical Engineering Design
Dana Manalang – System Engineer – Instrument Integration Testing